Complaint Handling and Redressal Standards

Consumer Grievance Handling Procedure

Consumer Grievance Redressel Forum

Tips to Consumers

Safety Measures

Micro Feeder Franchise(MFF)

List of ATP centers

Interaction Meetings
with Consumers

Online Consumer Services

Frequently Asked Questions

Manual for Maintenance of Distribution System

Safety Manual

Complaint Handling and Redressal Standards relating to distribution and supply of power

Home » About Us » BESCOM - Complaint Handling Procedure

Sl.
No.
Nature of ComplaintRedressal standards
(indicative maximum time limit for rendering service)
Primary responsibility centres where to lodge complaint and for redressalNext higher authority
AFailure of power supply due to:
1Fuse of call at aerial cutouts / sealable cutouts CCCD (Central Consumer Complaints Division)/Service station of the Sub-division. A.E(O&M)/J.E(O&M)/Section Officer/Lineman in the lineman campAEE(Ele) of the sub-division
a) Towns and citiesa) 4 Hours
b) Rural areasb) 24 Hours
2Snapping of wire CCCD (Central Consumer Complaints Division)/Service station of the Sub-division. A.E(O&M)/J.E(O&M)/Section Officer/Lineman in the lineman campAEE(Ele) of the sub-division
a) Towns and citiesa) I. De-energisation in case it is not de-energized automatically, immediately on receipt of the information.
II. Restoration of power supply within 6 hrs.
b) Rural areasa) I. De-energisation in case it is not de-energized automatically, immediately on receipt of the information.
II. Restoration of power supply within 6 hrs.
3Failing of trees on overhead lines (without breaking of poles) CCCD (Central Consumer Complaints Division)/Service station of the Sub-division. A.E(O&M)/J.E(O&M)/Section Officer/Lineman in the lineman campAEE(Ele) of the sub-division
a) Towns and citiesa) I. De-energisation in case it is not de-energized automatically, immediately on receipt of the information.
II. Restoration of power supply within 10 hrs.
b) Rural areasa) I. De-energisation in case it is not de-energized automatically, immediately on receipt of the information.
II. Restoration of power supply within 24 hrs.
4Fire due to short circuit of LT lines consequent to loose spans and touching of tree branches CCCD (Central Consumer Complaints Division)/Service station of the Sub-division. A.E(O&M)/J.E(O&M)/Section Officer/Lineman in the lineman campAEE(Ele) of the sub-division
a) Towns and citiesa) 6 Hours
b) Rural areasb) 12 Hours
5Interruptions due to breakdown of CCCD (Central Consumer Complaints Division)/Service station of the Sub-division. A.E(O&M)/J.E(O&M)/Section Officer/Lineman in the lineman campAEE(Ele) of the sub-division
I) 11 KV line overhead 
a) Towns and citiesa) 6 hours
b) Rural areasb) 6 hours
II) HT U.G.Cable faults 
In all towns and citiesTemporary arrangement for restoration of power supply within 24 hours and rectification of cable fault within 24 hours
III) Failure of Transformer 
a) Towns and citiesa) 24 hours
b) Rural areasb) 72 Hours
IV) LT Line 
a) Towns and citiesa) 6 hours
b) Rural areasb) 24 hours
V) Service main both overhead and underground 
a) Towns and citiesa)
i) Overhead     i) 24 hours
ii) U.G.Cable     ii) Temporary arrangement for restoration of power supply within 24 hours and rectification of cable fault within 3 days
b) Rural areasb) 48 hours
VI) Burnt out metersSubject to payment of meter cost as per Section 28 of KERC (ES&D) code, 2000-01
a) Towns and citiesa) 24 hours
b) Rural areasb) 48 Hours
6I) Street lights not functioning   
a) Within Bangalore Mahanagara Palike (BMP) area and wherever street lights are being maintained by local authoritya) To report to BMP / Local authority street light maintenance office in that locality - 24 hoursa) BMP local office / local authorityAEE or BMP / Local authority. IN charge of street lights.
b) At adjoining places of Bangalore other than BMP area.b) 24 hoursCCCD (Central Consumer Complaints Division)/Service station of the Sub-division. A.E(O&M)/J.E(O&M)/Section Officer/Lineman in the lineman campAEE(Ele) of the sub-division
c) Towns and citiesc) 48 Hours  
d) Rural areasd) 48 Hours  
II) Replacement of lamps and street light fittings   
a) Within Bangalore Mahanagara Palike (BMP) area and wherever street lights are being maintained by local authoritya) To report to BMP / Local authority street light maintenance office in that locality - 24 hours after supply of bulbs / lamps and accessories by BMP / local authoritya) BMP local office / local authorityAEE or BMP / Local authority. IN charge of street lights.
b) Towns and citiesb) 24 Hours after supply of fittings by local authorityCCCD (Central Consumer Complaints Division)/Service station of the Sub-division. A.E(O&M)/J.E(O&M)/Section Officer/Lineman in the lineman campAEE(Ele) of the sub-division
c) Rural areasc) 48 Hours after supply of fittings by local authority
BDisconnection and Reconnection
1Reconnection after payment of dues to KPTCL Both for Towns, Cities and Rural areasi) 24 hours if the disconnection period is not exceeding six monthsAAO of the sub-division / A.E.(O&M) / J.E.(O&M) / Section OfficerAEE(Ele) of the sub-division
ii) 48 Hours if the disconnection period is exceeding six months:
a) in cases where agreement is not terminated, the consumer shall clear outstanding arrears, produce interior wiring fitness certificate issued by the licensed electrical contractor.
b) in cases where agreement is terminated, the consumer shall apply afresh as per section 4.12(V) of KERC (ES&D) code,2000-01
2Reconnection when disconnected by oversight (Exceptional cases) even though bill amount is paid AAO of the sub-division / A.E.(O&M) / J.E.(O&M) / Section OfficerAEE(Ele) of the sub-division
a) Towns and Citiesa) 6 hours
b) Rural areasb) 24 hours
CVoltage Complaints
1Low Voltage Complaints15 days in case of local problem and 6 months in cases requiring augumentation of distribution systemCCCD (Central Consumer Complaints Division)/Service station of the Sub-division. A.E(O&M)/J.E(O&M)/Section Officer/Lineman in the lineman campAEE(Ele) of the sub-division
Both for Towns, cities and rural areas
2Voltage Fluctuations CCCD (Central Consumer Complaints Division)/Service station of the Sub-division. A.E(O&M)/J.E(O&M)/Section Officer/Lineman in the lineman campAEE(Ele) of the sub-division
a) Towns and citiesa) 4 days
b) Rural areasb) 8 days
DMetering and Meter Reading
1Replacement of non-recording meters and other faulty meters where supply is not affected. A.E.(O&M) / J.E.(O&M) / Soujanya Counter / Section OfficerAEE(Ele) of the sub-division
a) Towns and citiesa) 7 days
b) Rural areasb) 3 days
2Not reading the installations on the dates fixed for meter reading AAO / SA of the accounting unit / Soujanya Counter / A.E.(O&M) / J.E.(O&M) / Section OfficerAEE(Ele) of the sub-division
a) Towns and citiesa) 2 days
b) Rural areasb) 3 days
3Accidental breakage of seals provided to the meter on report by the consumer where no tampering of meter is suspected. Both for Towns, cities and rural areaInspection and report within 24 horus and replacement of meter within 8 daysA.E.(O&M) / J.E.(O&M) / Soujanya Counter / Section OfficerAEE(Ele) of the sub-division
EVerification of Bills
1Mistakes in totaling by the Meter reader while issuing the bills. A.E.(O&M) / J.E.(O&M) / Soujanya Counter / Section OfficerAEE(Ele) of the sub-division
a) Towns, cities and rural areasa) on the same working day
b) Rural areas where there is no a/c unitb) 2 working days
2Wrong calculation by the MR while issuing the bills and use of wrong meter constant AAO / SA of the accounting unit / Soujanya Counter / A.E.(O&M) / J.E.(O&M) / Section OfficerAEE(Ele) of the sub-division
a) Towns and citiesa) on the same working day
b) Rural areas where there is no a/c unitb) 3 working days
3Wrong recording of reading by Meter reader AAO / SA of the accounting unit / Soujanya Counter / A.E.(O&M) / J.E.(O&M) / Section OfficerAEE(Ele) of the sub-division
a) Towns and citiesa) 2 working days
b) Rural areasb) 8 working days
4Excessive billing. Both for towns, cities and rural areasOn the same dayAAO / SA of the accounting unit / Soujanya Counter / A.E.(O&M) / J.E.(O&M) / Section OfficerAEE(Ele) of the sub-division
5Amount already paid by consumer shown as arrears (provided the bill amount is paid at the sub-division where the bill is issued).
Both for towns, cities and rural areas
On the same working dayAAO / SA of the accounting unit / Soujanya Counter / A.E.(O&M) / J.E.(O&M) / Section OfficerAEE(Ele) of the sub-division
6Wrong application of tariff AAO / SA of the accounting unit / Soujanya Counter / A.E.(O&M) / J.E.(O&M) / Section OfficerAEE(Ele) of the sub-division
i) where field report is not necessary. Both for towns, cities and rural areason the same working day
ii) where field report is necessary. Both for towns, cities and rural areas8 working days
7Posting of wrong initial reading. Both for towns, cities and rural areasOn the same working dayAAO / SA of the accounting unit / Soujanya Counter / A.E.(O&M) / J.E.(O&M) / Section OfficerAEE(Ele) of the sub-division
8Showing the short claims in the monthly bill without furnishing the details to the consumer. Both for towns, cities and rural areasDetailed statement shall be furnished within 3 working days both in case of computer billling and manual billingAAO / SA of the accounting unit / Soujanya Counter / A.E.(O&M) / J.E.(O&M) / Section OfficerAEE(Ele) of the sub-division
9Wrong postings, i.e., postings of receipts to wrong R.R.Nos. both for Towns, cities and rural areasOn the same working dayAAO / SA of the accounting unit / Soujanya Counter / A.E.(O&M) / J.E.(O&M) / Section OfficerAEE(Ele) of the sub-division
10Discrepancies in billing like improper billing of non-recording period of meters (MNR), not issuing the average bills for the door lock cases etc. Both for towns, cities and rural areasOn the same working dayAAO / SA of the accounting unit / Soujanya Counter / A.E.(O&M) / J.E.(O&M) / Section OfficerAEE(Ele) of the sub-division
FNew connections: Service Standards
1Time frame to furnish feasibility report for arranging power supply and issue of power sanction letter. Both for towns, cities and rural areas6 working daysA.E.E(E) / A.E(T) of the sub-divisionE.E of the Division
a) Domestic Lighting
b) Commercial Lighting7 working days
c) A.E.H
d) LT Power
e) IP sets / street lights
f) Buildings, Regn. 9.00 -15 days
g) Layouts, Regn. 10.0030 working days
h) HT / EHT Power15 / 30 working days
i) Temporary Lighting / Power2 working days
2Time frame for servicing of new installation: Total period allowed from teh date of receipt of C.R/W.D., Agreement, payment of deposits. Both for Towns, cities and rural areas15 working days plus time required for inspectorate approvalA.E.E(E) / A.E(T) of the sub-divisionE.E of the Division
a) Dom / Com Ltg. / AEH - 30 days
b) LT Industries - 15 days plus period required for execution of service line work.
c) IP sets / R.E / Street lights - As per priority seniority and Annual Target
d) H.T. Power - 15 days plus period required for execution of service line work
e) EHT Power - 15 days plus period required for execution of service line work.
f) Temporary power supply - Upto 5 KW - 3 days, Upto 25 KW - 10 days, Upto 50 KW - 20 days
g) Tatkal Scheme applicable for dom, com, AEH ltg. - 8 days
3Opening of test report of the new installations immediately after service and issuing the first bill - First meter reading date after 30 days15 daysAAO / SA of the sub-divisionAEE(Ele) of the sub-division
GAppeal Cases
1Deciding the appeal casesa) First Appellate Authority - within 120 days from the date of filing the appealSecretary, Corporate Office of the licenseeC.M.D. of the Licensee
b) Second Appellate Authority - within 60 days from the date of filing the appeal
HGeneral
1Refund of advance consumption charges collected in respect of temporary installations - 2 months7 working daysAAO / SA of the a/c unit and A.O. I/A of the divisionAEE(Ele) of the sub-division
2Payment of solatium in case of electrical accidents:15 working daysSEE, of the circleCEIG
a) Payment of solatium in cases where it is established beyond doubt that the electrical accident is not due to the fault on the part of the victim: shall be paid immediately without waiting for the report of Chief Electrical Inspector to the Government
b) In other cases solatium shall be paid within 30 days from the report of the CEIG. Note: The CEIG shall send his report within one month from the date of accident
3Discoureous behaviour of staffTo enquire within a week and take suitable action and to inform the complainantAEE of the Sub-divisionEE of the Division
4Modification of the existing connection:7 working daysAAO / A.E(O&M)/J.E.(O&M)/Section OfficerAEE of the sub-division
a) Transfer of installation - 20 days
b) Reduction of load / surrender of power supply - 2 months
c) Shifting of meters and meter board - 10 days
d) Conversion of installation from one tariff to another tariff - 15 days
5Removal of the meter at the request of the consumer - 15 days7 working daysAAO / A.E(O&M)/J.E.(O&M)/Section OfficerAEE of the sub-Division
6Issue of certificates as per section 30.16 of KERC (ES&D) code, 00-01 - 2 working days7 working daysAAO / SA of the a/c unitEE of the Division
7Refund of deposit - 60 days7 working daysAEE / AAO / SA of the sub-divisionEE of the Division
8Withdrawal of demand and refund - 60 days7 working daysAEE / AAO / SA of the sub-divisionEE of the Division
9Any complaint not covered specifically in the above - 30 days7 working daysAAO / AAO / SA of the sub-division EE of the Division